A customer sends a corrective action request. The reply says the bad product was sorted and the operator was retrained. The customer rejects it. This happens because three different things are being treated as one.

The three terms

  • A correction fixes this instance. Sort the pallet, rework the batch, replace the order.
  • A corrective action removes the cause, so the problem does not come back.
  • A preventive action removes the cause of a problem that has not happened yet.

An example

A pipe joint leaks onto the floor. Mopping the floor is the correction. Replacing the failed seal, and finding out why it failed, is the corrective action. Checking the other joints of the same age is the preventive action.

Why customers push back

Sorting and replacing are corrections. They are necessary, and the customer still has no reason to believe the problem will not return. Retraining on its own is the weakest corrective action, because it relies on memory. Stronger actions change the process: remove the possibility, detect the error automatically, or make the mistake obvious.

What a good reply contains

  • The problem in facts: what, where, when, how many.
  • What was contained, and how.
  • The root cause, reached by asking why until you arrive at something you can change.
  • The action taken on that cause, with a date.
  • How you will check that it worked.

Close it properly

A corrective action is finished when you have checked, some weeks later, that the problem has not come back. Write down what you checked and the date.